- NET PRESENT VALUE OF PROJECT
-
- MOST INVESTMENT PROJECTS INVOLVE SOME INITIAL COST AND THEN
- INFLOWS AND OUTFLOWS IN THE FUTURE UNTIL SOME TIME WHEN
- WHEN THE INVESTMENT IS TERMINATED. BASED UPON THE RISK IN THE
- ORIGINAL INVESTMENT THE INVESTOR SHOULD HAVE SOME REQUIRED
- RATE OF RETURN HE/SHE DESIRES TO EARN FROM THE INVESTMENT.
- IF THE PRESENT VALUE OF THE CASH FLOWS FROM THE PROJECT
- ARE POSITIVE WHEN USING THE REQUIRED RATE AS THE DISCOUNT RATE
- THEN THE PROJECT IS A REASONABLE ONE TO INVEST IN.THIS
- PROGRAM COMPUTES THE PRESENT VALUE OF SUCH A PROJECT. IF THE
- USER SETS THE INITIAL INVESTMENT EQUAL TO 0 THEN THE PRESENT
- VALUE EQUALS THE MAXIMUM AMOUNT TO BE PAID INITIALLY FOR THE
- PROJECT.
-
- PRESS ENTER TO BEGIN?
- INPUT FOR NEW PROJECT
-
- INPUT REQUIRED RATE OF RETURN (%) ? 5
-
- INITIAL CASH COST OF PROJECT ? 123000
- ENTER CASH FLOW FOR PERIOD 1 (-.01 TO END)? 11111
- ENTER CASH FLOW FOR PERIOD 2 (-.01 TO END)? 22222
- ENTER CASH FLOW FOR PERIOD 3 (-.01 TO END)? 33333
- ENTER CASH FLOW FOR PERIOD 4 (-.01 TO END)? 44444
- ENTER CASH FLOW FOR PERIOD 5 (-.01 TO END)? 55555
- ENTER CASH FLOW FOR PERIOD 6 (-.01 TO END)? -0.01
-
- NET PRESENT VALUE AT 5 % INTEREST EQUALS $16625
- DO YOU WANT ANOTHER NPV FOR SAME CASH FLOWS BUT CHANGING INTEREST RATE (Y
- /N) ? N
-
- INPUT FOR NEW PROJECT
-
- INPUT REQUIRED RATE OF RETURN (%) ? 0
-
|